9. Cost Analysis
The tools that support this requirement model costs of generic
OOTWs for use in national force structure planning, input to
decisions on engaging in an OOTW, and to estimate comparative
costs during mission planning. Historical data are required.
Elements include:
- · opportunity cost and
· comparative costs of different force structures.
The tool requirements are provided by the OOTW
analysis tasks that it must support.
· Estimate cost of operation, task # 1.2: Estimate the
cost of operations, including both direct and indirect costs.
The MORS OOTW workshop yielded a refinement of Task 1.2, estimate
cost of operation.
- Task 1.2.1 Generic OOTW Cost: Estimate the cost of
a generic OOTW of a given category, e.g. NEO. The costs
are only "incremental costs," i.e., those over
and above those in the Congressional Budget. Accuracy of
+/- 50%. Who: NCA, OSD, Joint Staff, CINCs, Services.
- Task 1.2.2 Cost Input for Decision to Engage in an
OOTW: Estimate the incremental cost of an actual
proposed OOTW. The costs will need to be revised as more
information becomes available. Accuracy of +/- 50% or
better. Needs to consider roles of NGOs, PVOs and allies.
An "end-state" and transition plan must be
defined for the appropriate costs to be included. Who:
NCA, OSD, Joint Staff, CINCs.
- Task 1.2.3 Alternative COA Costs: Estimate the
relative costs of alternative COAs for an actual OOTW.
The costs required may be full costs, rather than
incremental costs. For example, options of contracting
for services must be compared against full costs for
other options. However, only variable costs need to be
computed. Accuracy needs to be +/- 30%. Who: CINCs,
components and Services.
- Task 1.2.4 Cost Recovery: Calculate (estimate) the
cost of a completed (or partially completed) OOTW for
purposes of recovering costs. Legal constraints often
allow only incremental costs to be recovered; however, in
some instances full costs may be recoverable. Accuracy
should be +/- 30% or better. Who: OSD, State Department,
Services down to individual units.
- Task 1.2.5 Budgeting for an OOTW: Estimate the
cost of a future (or ongoing) OOTW for Congressional
Budgeting purposes. For most appropriations, these costs
will be full costs. Accuracy of +/- 50%. Who: Service
Unit involved.
- Task 1.2.6 OOTW Cumulative OOTW Cost Impacts:
Estimate the cumulative costs of participating in OOTWs.
The assumption is that the incremental costs of the
individual OOTWs do not capture equipment depreciation,
readiness losses, increased reserve recruitment and
training costs, and perhaps other costs. Accuracy of +/-
50%. Who: Programmers, Services, OSD including Reserves.
- Task 1.2.7 "Actual" Cost Accounting for
OOTWs: Account for both incremental and full costs as
they occur. Reconcile with earlier estimates. Accuracy of
+/- 5% or better. Who: Controller, auditors.
This is a medium-complexity model. The priority is 3;
modelability is Yellow (Y); and the data availability is
Expensive ($). Do it now.
The table below will be updated as information is posted on
the bulletin board for each requirement.
Table 9. Cost Estimation Tools
ID |
Tasks Addressed |
1.2.1 |
1.2.2 |
1.2.3 |
1.2.4 |
1.2.5 |
1.2.6 |
1.2.7 |
CANTELOUPES |
|
Army |
|
|
Army |
|
|
database |
|
|
|
|
|
|
|
JSORTS |
|
|
|
|
|
|
|
SOFCOST |
|
SOF |
|
|
SOF |
|
|
spreadsheet |
|
|
|
|
|
|
|
COST |
Y |
Y |
|
|
|
|
|
OOTW Tool Home Page